Heat Substations

Investor:
The Voivodship Heating Energy Company in Legnica
The task:
Construction of the 25 MW steam-water heat transfer station in the Central
Heating Plant in Legnica
Year: 2006
Investor:
Barlinek in Barlinek
The task:
Construction of 8 MW water heat transfer station on the premises
Year: 2006
Investor:
Construction of 10.5 MW water heat transfer station on the premises
The task:
Barlinek in Barlinek
Year: 2004
Investor:
Bridgestone in Poznań
The task:
Construction of 1 MW steam-water heat transfer station on the company\'s
premises in Poznań
Year: 2003
Investor:
Heating Company in Jelenia Góra
The task:
Construction of 36 MW steam-water heat transfer station on the premises of the
heating power plant
Year: 2002